On Air Now

Current Show

WSAU Feedback   8:00 AM - 9:00 AM

Call WSAU Feedback at 715-845-2155.

Show Info »

Upcoming Shows

Program Schedule »

Listen

Listen Live Now » 550 AM Wausau, WI 99.9 FM Stevens Point, WI

Weather

Current Conditions(Wausau,WI 54403)

More Weather »
61° Feels Like: 61°
Wind: W 8 mph Past 24 hrs - Precip: 0.01”
Current Radar for Zip

Today

Isolated Thunderstorms 79°

Tonight

Mostly Clear 56°

Tomorrow

Scattered Thunderstorms 80°

Alerts

Breaking News

BREAKING NEWS / URGENT: The State Supreme Court upholds Act 10, Voter ID, and the state's domestic partnership registry

MADISON, Wis (WSAU)  - The Wisconsin State Supreme Court upheld Act 10, the state law that limits the collective bargaining rights of state employees. The law from three years ago sparked protests at the state capital and led to the recall attempt against Governor Scott Walker. The court's ruling in favor of Act 10 was 5-2. Justice Michael Gableman wrote the lead opinion, which was also signed by Justices David Prosser, Pat Roggensack and Annette Ziegler. Justice Patrick Crooks concurre...

Read More »

Marshfield construction project has Wednesday community meeting

by
Marshfield city logo.
Marshfield's Chestnut Avenue, before construction (Spring 2013)
Chestnut Ave. Marshfield WI
Marshfield city logo.

MARSHFIELD, WI (WSAU)  -  Marshfield’s biggest street reconstruction project of the summer is scheduled to start on Monday; but before actual work starts on the reconstruction of South Chestnut Avenue, an informational meeting is set for 5:00 Wednesday afternoon at Marshfield City Hall.

City engineer Tom Turchi says both residents and business owners may want to attend to learn how to deal with the summer-long project.  According to Turchi, “Wednesday night’s public informational meeting is going to start with the contractor basically going through his construction schedule.

This project has been divided into several phases, and he’s got a tentative schedule for those phases. Each of those phases will have different modes of access for businesses and residents along the project. We’ll have a copy of the final plan, and we’ll be going through any questions. Residents can look at those plans as they relate to their specific property or business.”

The contractor on the $3-million dollar, six-month long reconstruction project is A-1 Excavators of Bloomer; and Turchi says the contractor will hold weekly meetings throughout the summer to update the public. South Chestnut Avenue is utilized by more than 3,000 vehicles daily, and is home to the city’s only post office, police station, and numerous other businesses.