On Air Now

Current Show

Coast to Coast AM   12:00 AM - 5:00 AM

Contact Coast to Coast AM at 1-800-825-5033

Show Info »

Upcoming Shows

Program Schedule »

Listen

Listen Live Now » 550 AM Wausau, WI 99.9 FM Stevens Point, WI

Weather

Current Conditions(Wausau,WI 54403)

More Weather »
60° Feels Like: 60°
Wind: W 3 mph Past 24 hrs - Precip: 0.01”
Current Radar for Zip

Tonight

Clear 53°

Tomorrow

Mostly Sunny 75°

Wed Night

Clear 53°

Alerts

St. Croix River bridge construction halted by zebra mussels on barges

by
Minnesota DNR logo
Minnesota DNR logo

ST. CROIX, WI (WTAQ) - A Wisconsin firm will de-contaminate almost 100 construction barges used to ship building materials to the site of the new Saint Croix River bridge near Hudson.

Preliminary work on the project was halted, after Minnesota’s DNR found dead invasive zebra mussels on six-of-eight barges that were hauled by trucks.

None of the barges reached the river.

They were trucked to the site from Oshkosh and Milwaukee.

The DNR’s Chris Niskanen said Edward Kraemer-and-Sons of Plain property treated the hulls of the barges with 190-degree water – but they did not scrape the hulls.

Inspectors noticed the zebra mussels this week at a construction staging area on the Minnesota side of the river, and they notified that state’s DNR.

Kraemer’s Bob Beckel said his firm will make sure the cleaning problem does not happen again.

The DNR is investigating the incident.

Even if they got into the river, Niskanen said the waterway would not have been at risk.

It’s the second major delay for the four-lane Saint Croix bridge. The first came as the result of bidding dispute by a Minnesota contractor that went to federal court last month.

Wisconsin and Minnesota are splitting the cost of the new bridge, totaling around $620-million.

It’s due to open in 2016.

Comments