MARSHFIELD, WI (WSAU) — One of Marshfield’s busiest east-side intersections closed on Monday for reconstruction, and city engineer Tom Turchi says traffic will be detoured away from the corner of Fourth Street and Peach Avenue for much of the summer.
“On the Fourth Street/Peach Avenue signal upgrade and intersection reconstruction project, this morning we closed that and put a detour in place. I’m anticipating the traffic signals will be taken out of service later this week,” Turchi said.
‘We Energies’ is already doing work in the area before the complete reconstruction of the intersection including new stoplights starts in early July.
According to Turchi, “We Energies is onsite and is starting preparation for relocation of gas mains, in advance of Earth’s construction on that project, which is planned to start on July 5th.”
During the project, traffic will be detoured to Third and Fifth Streets.